Roof squaresWorked exampleGuide notes
Two shingle makers add 10% to 15% for waste to a roof’s squares, and the asphalt roofing trade group puts trim waste at 2% to 10%
On an example twin, the roof’s pitch adds 1.6 squares to the plan area, and waste allowances from 2% to 15% move the order by 3 bundles.
On the example twin, pitch adds 1.6 squares and waste adds up to 1.4 more
A roofer orders shingles by the square, 100 square feet of roof surface, and then adds extra for the pieces cut away at valleys, vents and edges. The Asphalt Roofing Manufacturers Association, the trade group for asphalt shingle makers, puts that trim waste at 2% to 10% in its Residential Asphalt Roofing Manual. GAF and IKO, two shingle makers, tell buyers on their own websites to plan on 10% to 15%.
On an example twin worked through below, the full range from 2% to 15% changes the order by 3 bundles, or one square. The roof’s pitch, or steepness, adds 1.6 squares to the area a level plan of the same roof shows.
Question 7 on the borough’s form asks for squares installed, each 10 feet by 10 feet
Conshohocken’s Roof Permit Application Addendum, revised January 2, 2025, goes with every re-roofing permit in the borough. Question 6 asks for the approximate pitch of the roof. Question 7 asks how many squares will be installed and defines a square as 10 feet by 10 feet. The site’s walk through a roofing quote line by line covers the rest of the form.
The form asks for squares installed. Waste is cut off and thrown away, so it is not installed.
A quote may give squares installed, squares ordered, or both, and the gap between them is the waste allowance.
An 8 in 12 roof has 20.2% more surface than its level plan
The manual describes measuring a roof by splitting it into rectangles and triangles, adding up their areas and dividing by 100 to get squares. It recommends that a roofing professional take the measurements and advises homeowners against climbing up to do it.
A sloped roof has more surface than its level plan shows. IKO publishes a table of factors to multiply the plan area by for each pitch. Pitch is written as the rise in inches over 12 inches of run, so 8 in 12 rises 8 inches for every foot.
The factor is the length of the sloped line divided by its level run, the square root of the rise squared plus 144, divided by 12.
The area factor runs from 1.031 at 3 in 12 to 1.414 at 12 in 12
Area factor by pitch, both columns
| Pitch | Formula | IKO | Extra |
|---|---|---|---|
| 3 in 12 | 1.031 | none | 3.1% |
| 4 in 12 | 1.054 | 1.054 | 5.4% |
| 5 in 12 | 1.083 | 1.083 | 8.3% |
| 6 in 12 | 1.118 | 1.118 | 11.8% |
| 7 in 12 | 1.158 | 1.157 | 15.8% |
| 8 in 12 | 1.202 | 1.202 | 20.2% |
| 9 in 12 | 1.250 | 1.250 | 25.0% |
| 10 in 12 | 1.302 | 1.3052 | 30.2% |
| 11 in 12 | 1.357 | 1.356 | 35.7% |
| 12 in 12 | 1.414 | 1.414 | 41.4% |
The trade group puts trim waste at 2% to 10%, and GAF and IKO say 10% to 15%
The manual says the extra shingles depend on how many valleys, dormers, hips and roof penetrations the roof has. “In most cases it should be between 2% and 10%,” it says. GAF’s blog post on bundles says contractors usually include 10% to 15% for trim and waste.
The two shingle makers’ ranges start at 10%, where the trade group’s range ends
IKO’s page calls 10% to 15% a general range, says smaller roofs tend to have a higher waste factor than larger ones, and suggests keeping a leftover bundle in a dry place for later repairs.
Most shingles come 3 bundles to a square, and heavier ones take up to 5
GAF and IKO both say most standard shingles, three-tab and architectural, come three bundles to a square, and that heavier specialty shingles can take up to five. GAF lists its Timberline HDZ at three bundles and 64 shingles per square, and its Woodland line at four bundles and 56 shingles per square.
IKO’s Armourshake takes 5 bundles to a square, at 20 square feet a bundle
IKO says the coverage per bundle must be printed on the wrapper, and that the number of shingles in a bundle tells you little because shingle sizes differ.
The twin’s order runs from 30 bundles at 2% waste to 33 at 15%
The two houses here are made up, with round numbers. The twin is one half of a pair of attached houses. Its gable roof measures 22 by 36 feet on a plan, including a 1-foot overhang at the eaves, and it is pitched 8 in 12. The rowhome’s main roof is 16 by 30 feet on a plan, pitched 6 in 12, with a 1-foot overhang at the eaves and a party wall on each side.
The twin’s plan area is 792 square feet. Multiplied by 1.202 for its pitch, the surface is about 952 square feet, or 9.52 squares installed. With 2% for waste the order comes to 9.71 squares and 30 bundles of a three-bundle shingle. With 15% it is 10.95 squares and 33 bundles. Measured on the plan alone, without the pitch factor, the same roof would show 7.92 squares.
Going from 2% to 15% waste adds 3 bundles to the twin and 2 to the rowhome
The rowhome’s 480 square feet of plan becomes about 537 square feet of surface at 6 in 12, or 5.37 squares. It takes 17 bundles at 2% waste and 19 at 15%.
The twin’s eaves take two courses of membrane to reach 24 inches inside the wall
IKO notes that most accessories are ordered by length, so a roofer also measures the eaves, rakes, valleys, ridges and hips. The rakes are the sloped edges at a gable end. Drip edge, the metal strip at the roof’s edges, runs along the eaves and rakes, and IKO uses the same total for starter strip, the first row of material at the eave. IKO lists a bundle of its starter shingles at 123 linear feet, a roll of its synthetic underlayment at 1,000 square feet and a roll of its ice and water protector at 65 feet long.
The borough’s addendum requires ice and water shield, a self-adhering membrane that keeps water backed up behind ice from leaking through, at least 24 inches inside the exterior wall line. CertainTeed sells its Vycor membrane in rolls 36 inches wide.
One 36-inch course stops short of 24 inches inside the twin’s wall, so it takes a second
On the twin, the membrane has to run 1 foot of overhang plus 2 feet inside the wall, 3 feet measured level and about 3.61 feet along an 8 in 12 slope. One 36-inch course falls short, so the roofer adds a second course, lapped over the first; the manual gives a 2-inch lap or whatever the maker specifies. Two courses along 44 feet of eave come to 88 linear feet, or two 65-foot rolls. The rowhome needs 3.35 feet along its 6 in 12 slope and also takes two courses.
The twin needs 9.52 squares installed and the rowhome 5.37, line by line
| Line | Twin | Rowhome |
|---|---|---|
| Plan and surface | ||
| Plan size with overhangs (ft) | 22 x 36 | 16 x 30 |
| Plan area (sq ft) | 792 | 480 |
| Pitch | 8 in 12 | 6 in 12 |
| Roof surface (sq ft) | 952 | 537 |
| Shingles | ||
| Squares installed | 9.52 | 5.37 |
| Squares ordered with 2% waste | 9.71 | 5.47 |
| Squares ordered with 10% waste | 10.47 | 5.90 |
| Squares ordered with 15% waste | 10.95 | 6.17 |
| Bundles at 3 per square with 2% waste | 30 | 17 |
| Bundles at 3 per square with 10% waste | 32 | 18 |
| Bundles at 3 per square with 15% waste | 33 | 19 |
| Bundles at 5 per square with 10% waste | 53 | 30 |
| Eaves, rakes and ridge | ||
| Eave length (ft) | 44 | 32 |
| Slope distance from eave edge to 24 in. inside the wall (ft) | 3.61 | 3.35 |
| Courses of 36 in. eave membrane | 2 | 2 |
| Eave membrane (linear ft) | 88 | 64 |
| Rake length (ft) | 43.3 | 0 |
| Drip edge and starter (linear ft) | 87.3 | 32 |
| Ridge (ft) | 22 | 16 |
Worked example in round numbers. Bundles are rounded up to whole bundles. Eave membrane is measured along the slope to a point 24 inches inside the exterior wall, as the borough’s addendum requires, in rolls 36 inches wide. Download the data (CSV)
What to ask for in a quote
- Ask for the pitch and the squares installed, the same two numbers the borough’s form asks for, and then for the squares ordered. The difference is the waste allowance, and you can compare it to the 2% to 15% the sources give.
- Ask which shingle is planned and how many bundles make a square for it. Compare two quotes by squares, because a bundle of one shingle can cover less roof than a bundle of another.
- Ask how many courses of ice and water shield the roofer will lay at the eaves to reach 24 inches inside the wall.
- If two roofers count different squares for the same roof, ask each how they measured: on the roof, from plans or from an aerial measurement service.
Caveats
Both houses are examples, and a real roof with dormers, valleys, chimneys or a low-slope rear section takes more waste and more flashing than these plain gables. Dimensions taken from the ground are approximate. Bundle counts per square differ by product, so the wrapper of the shingle being installed is the one to check. The waste ranges are general guidance from a trade association and two manufacturers; a roofer’s own figure for a given roof can fall outside them. The guide to roofing permits covers the nearby townships.